Phases I – II Water Supply Project (WSP)
Date of Contract: Phase I 2001 - Phase II 2002 Handover Date: Phase I 2003 - Phase II 2003 Contract Value: 3.700.000. -USD
Employer:
Kayseri Water and Sewerage Authority (KASKI) - Turkey
Nature of the Work
Piomak, within the scope of the Kayseri WSP, provided turnkey pump stations for Zone DZ3, the city’s new residential area. Phase I was to supply and install 5 submersible pumps including pipes and fittings and electro control systems at the field sites.
Two complete high lift pumping stations with 7 horizontal split case pumps. The 3 pumps in the high lift PS have a power rating of 200 kW; 2 pumps have a power rating of 30 kW; and the other 2 pumps of 37 kW.
In Phase II of the WSP, Piomak completed a turnkey overhauling works which included 6 high lift pumping stations and related utilities.
The project was to supply and install 11 new submersible pumps including pipes and fittings; an electro control system at well field sites; more than 120 motorized valves with diameter of 400 up to 1000 mm; field instrumentation; new electrical installation; new electrical distribution and control panels; and 5 generator sets for emergency power supply.
The total project was financed by the German development bank Kreditanstait fur Wiederaufbau (KfW).