Kırsehir Turnkey Wastewater Treatment Plant
Date of Contract: October, 2008 Handover Date: December, 2010 Contract Value: 3.800.000.-USD
Employer:
Ankara Water and Sewerage Administration (ASKI) - Turkey
Nature of the Work
Piomak is a member of the joint venture that was awarded the contract for this project. The constructed plant has a treatment capacity of 25.000 m³/day based on the long aeration process system. In this plant, the active sludge system will also be applied.
Besides being member of the joint venture, Piomak also provided the complete electrical system, field instrumentation, and the automation system to control more than 1.100 input/output control process signals. The total system is monitored and controlled by a Supervisory Control and Data Acquisition (SCADA) Computer Monitoring Station installed in the control room.