Water & Fuel Storage Tank Farms intended for Sudanese Thermal Power Generation Company – Garri III Power Plant
Date of Contract: November, 2016 Handover Date: December, 2018 Contract Value: 8.960.000, -USD
Employer:
SEMI INTERNATIONAL FZE, United Arab Emirates
Nature of the Work
Piomak completed the basic and detailed design of the fuel storage tank farm including the unloading system and firefighting system intended for the fuel tank farm intended for the Sudanese Thermal Power Generation (STPG) Company at the new Garri III Power Plant, 70 km from Khartoum.
Furthermore, Piomak within the same project had prepared the complete design works intended for the water tank farm.
Within the scope of the works specified in the contract, Piomak also completed the construction of the tank farm for the dikes and foundation, and the installation of the fuel unloading station and the steel tanks.
Accordingly, Piomak installed one 14.000 m³ raw water tank; one 2.500 m³ demin water tank; two 2.000 m³ service water tanks; one 20.000 m³ Light Diesel Oil (LDO) steel tank; two 20.000 m³ Heavy Fuel Oil (HFO) steel tanks, and the associated fuel unloading stations.