Water Supply Improvement Project in North Iraq Expansion of Erbil Water Treatment Plant (WTP)
Date of Contract: July, 2013 Handover Date: September, 2015 Contract Value: 6.500.000.-USD
Employer:
STFA - Fernas - Kalyon Joint Venture - Iraq
Nature of the Work
Piomak completed the EPC contract of electromechanical works for the daily 80.000 m³ capacity of the Water Treatment Plant (WTP), the river intake pumping station, the booster pumping station, and clear water reservoirs.
The project was to complete the 2nd phase of a plant in total of 160.000 m³/d to include all mechanical equipment, the erection and commission for the Water Supply Improvement Project in Kurdistan LOT 1 – Expansion of Erbil 3 Water Treatment Plant.
Piomak also supplied all the electrical systems, compromising 6 Medium Voltage transformers and Medium Voltage switchgear system, Medium Voltage electronic motor soft starters, complete Low Voltage, instrumentation and signal cabling, as well as a complete SCADA and automation system for both Phase I and Phase II.